Project Timeline
Please note that the timeline is subject to change for a variety of factors. The City will do its best to keep residents up-to-date on all developments.
This project is expected to take approximately one year from kick-off in September 2011 until final clean-up is finished by August 2012. Initial preparation work and work along the embankment wall will begin in September and extend into early November 2011.
A majority of the work along the bridges (viaducts) will take place in spring and early summer 2012. At times, the project sites will be bustling with activity, while at other times they will be quiet. CTA’s contractors completing the project, Kiewit Infrastructure Group, are trying to complete this critical project quickly and safely as possible with as minimal disruption as possible to Evanston residents' lives.
Spring 2012 Timeline for CTA Viaduct Project
March 2012
March 13-18, 2012 – Final foundation work on Southeast corner of Dempster Street Viaduct (four days closure with one day of clean-up for Dempster St. from Sherman Place to just west of bridge required)
Dempster Detour.pdf
March 19, 2012 - Staging area begins at Greenleaf Street site within the Jewel/Osco parking lot on Chicago Ave.
March 23, 2012 – Steel Delivery – Greenleaf Street
April 2012
April 16, 2012 (Old Date was April 9, 2012) - Staging areas begins at Grove Street (south side of Grove St. between Sherman Ave. and the viaduct)
April 18th, 2012 (Old Date was April 13th, 2012) - Steel Delivery – Grove Street will be closed near viaduct (Detour in effect)
Grove Detour.pdf
April 23th, 2012 (Old Date was April 16th, 2012) - Staging areas begins at Dempster Street (on Sherman Place from Dempster Street north approximately 120 feet will be closed)
April 25th, 2012 (Old Date was April 20th, 2012) - Steel Delivery – Dempster Street will be flagged and near viaduct (Slight Delays Possible)
East/west traffic will remain ongoing throughout the project on Greenleaf and Dempster Streets except when otherwise noted above. West bound traffic along Grove Street will remain throughout, but east bound traffic will be restricted until the project is completed unless otherwise noted above.
May 2012
Work continues at all three sites.
June 2012
Week of June 4th-10th - Roll-in of new viaduct at Greenleaf Street
- Greenleaf Street Site will be closed approximately with work running continuously for 48 straight hours from the evening of June 8th-June 10th.
- CTA service along the Purple Line will be disrupted for the weekend at this area with riders being bused between Main Street and Davis Street Stations
Greenleaf Detour1.pdf
Week of June 18th -24th - Roll-in of new viaduct at Dempster Street and Grove Street
- Grove Street and Dempster Street Sites will be closed approximately with work running continuously for 48 straight hours from the evening of June 22nd -June 24th.
- CTA service along the Purple Line will be disrupted for the weekend at this area with riders being bused between Main Street and Davis Street Stations
Dempster Detour & Grove Detour Please see links above
July – August 2, 2012
Clean-up work at all three sites
2011 - REVISED October 26, 2011
September/October 2011
Retaining wall work along Chicago Ave. (from Madison St. to South Blvd.) Approximately 6 weeks - NOW ENDING December 3rd.
Chicago Chicago Ave. Retaining Wall Work Site
• Closures of one southbound lane on Chicago Ave. to last for the entire six week period. NOW ENDING December 3rd.
Caisson work at Dempster St., Greenleaf St. and Grove St. to prepare for Purple Line Viaduct replacement in 2012. Caisson work involves placing a large cylindrical can into the ground, drilling and removing the earth from within the can and then finally filling the ground with concrete. It will serve as the foundation for the new CTA bridges.
Grove St. (From Elmwood Ave. to just east of the viaduct) to be closed to vehicular traffic for approximately two weeks beginning on October 10 through October 23rd. Now October 10 through October 30th.
Detour Map Grove Detour
Dempster St. (From Sherman Ave. to Sherman Place) to be closed to vehicular traffic for approximately two weeks beginning on October 24 through November 6th.
Now October 31st through November 18th.
Detour Map Dempster Detour.pdf
Greenleaf St. (From Custer Ave. to just east of the viaduct) to be closed to vehicular traffic for approximately two weeks beginning on November 7th through November 20th.
Now November 28 through December 16th.
Detour Map Greenleaf Detour1
*Pedestrian access will be maintained at all three locations
2012
March/April 2012
Staging area begins at all three sites.
- Greenleaf St. site (Jewel/Osco parking lot),
- Dempster St. site (on Sherman Place)
- Grove St. (south side of Grove St. between Sherman Pl. and the viaduct)
East/west traffic will remain ongoing throughout the project on Greenleaf and Dempster Streets. West bound traffic along Grove At. will remain throughout, but east bound traffic will be restricted until the project is completed. Please see the Detour page for further details.
April/May 2012
Work continues at all three sites.
May/June 2012
- Early summer roll-in of new viaduct at Greenleaf St. (approximately 48 hours over one weekend-TBD).
- Summer roll-in of new viaducts at Grove and Dempster Streets (done concurrently and in 48 hours over one weekend-TBD).
Summer 2012
Clean-up work at all three sites including some road closures.
For Questions
Please contact the 3-1-1 Call Center seven days a week, from 7 a.m. to 7 p.m. to speak with a customer service representative. The question will be routed to the appropriate city or CTA staff member for a timely response.
Additionally, residents can find information on the project through the City of Evanston's website, Facebook page as well as the Twitter handle @PurpleLineEV.
Sign up for Purple Line updates
Who is fixing the Viaducts?
Kiewit Infrastructure Group is a well-established transportation contracting company and has been selected to work with the CTA to complete Evanston’s Purple Line Viaducts.
Upcoming Events
-
May
11
Utilities Commission
7:15 AM -
May
11
Mexican "Mobile" Consulate/Consulado Movil de Mexico
11:00 AM -
May
11
Green Film Series
7:00 PM -
May
11
"Twelfth Night" on stage at NU
8:00 PM -
May
12
Downtown Evanston Farmers' Market
Recent News
- Temporary partial street closure on Main St. at Custer
- Downtown Evanston Organization, City Staff Pushing for Julius Meinl Coffee Shop to Come to Evanston
- E.P.D. Clergy Team Hosts - Police Appreciation Day on May 10th
- Evanston Police Announce Traffic Enforcement Initiative
- Workshop on Fair Lending and Mortgage Scams Set for May 17 at EPL