City to Begin Motor Fuel Tax Street Resurfacing Project the Week of June 15

Post Date:06/15/2020 1:53 PM

Beginning the week of June 15, the City will be contracting road resurfacing work on thirteen street segments throughout Evanston. This project will be completed over a twelve week period and construction will be done in two phases.

The actual date when construction is planned for each street will be noted on the temporary "NO PARKING" signs posted 48 hours prior to the start of work. The construction activities will create some inconvenience for abutting residents, but all attempts will be made to minimize these inconveniences. Construction zone daytime "NO PARKING" restrictions will be intermittent throughout the duration of the project; evening and night parking, 5 p.m. to 7 p.m., will always be available. Street sweeping and/or neighborhood parking restrictions will be waived for a one block radius around the construction zone when temporary daytime "NO PARKING" is in effect.

The funding for this project will come from the City’s Rebuild Illinois and Motor Fuel Tax Funds and there will be no direct charge for the property owners on these streets. Project work includes roadway base repair, sewer work, replacement of asphalt surface from curb to curb along with selected ADA sidewalk replacement and driveway aprons, and curb replacement as needed. Specific locations included in each phase of construction are listed below.

Phase 1 Streets 
Chancellor Street (Broadway Avenue to Eastwood Avenue)
Grant Street (Crawford Avenue to Cowper Avenue)
Lincolnwood Drive (Park Place to Isabella Street)
Park Place (Central Park Avenue to Hurd Avenue)
Park Place (Hurd Avenue to Lincolnwood Drive)
Pioneer Road (Simpson Street to Payne Street)
Pioneer Road (Noyes Street to Grant Street)
Wesley Avenue (Grove Street to Davis Street)

Phase 2 Streets
Callan Avenue (Mulford Street to Hull Terrace)
Grey Avenue (Dead End South to Greenleaf Street)
Darrow Avenue (Church Street to Lyons Street)
Lyons Street (Darrow Avenue to Dead End East)
Madison Street (Dodge Avenue to Dewey Avenue)

Contractor
The contractor for this project is J.A. Johnson Paving, 1025 E. Addison Court, Arlington
Heights, IL 60005.

City Monitoring
The project is under the supervision of the City’s Capital Planning & Engineering Bureau. The Resident Engineer in the field will be Pankaj Chokshi who will be directly responsible for all aspects of construction. For questions or concerns, please contact the Resident Engineer at 224-723-8237. For questions about the street resurfacing projects in general, contact Senior Project Manager Sat Nagar, P.E. at 3-1-1 or 847-448-4311.