Home MenuSheridan Rd. - Chicago Ave. Improvement Project
What's New in 2018?
Phase 3 of Sheridan Road Construction has Begun!
Project Summary:
Project Address:
-
Phase 1:
Chicago Avenue: Grove Street to south limit of Chicago/Sheridan Intersection
Dates: March 27, 2017 – June 12, 2017
-
Phase 2:
Sheridan Road: Chicago/Sheridan Intersection to Lincoln Street
Dates: June 19, 2017 – September 15, 2017
- Phase 3:
Sheridan Road – Lincoln Street to Ridge/Isabella Intersection
Dates: April 1, 2018 – October 19, 2018
Project Manager:
Sat Nagar
For questions, please call 847-448-4311 or contact us here.
Current Project Phase:
Construction
Public Meetings:
Project Plans:
Sheridan Road Bike Plan - North of Lincoln
Newsletters:
- October 24, 2016
- March 14, 2017
- August 1, 2017
- March 27, 2018
- June 19, 2018
Council Actions:
Award for Alternative Analysis - Christopher B. Burke Engineering, Ltd. - 04/28/14
Award of Construction Engineering - Phase I & II - Christopher B. Burke Engineering 12/08/14
- October 17, 2016
- October 24, 2016
Comments or Questions?